Downtown Phase 1 Construction Schedule

Preliminary ScheduleDate
Collection System Bids SubmittedMay 6, 2020
Wastewater Treatment Facility Bids SubmittedMay 13, 2020
ATM Supplemental FundingJune 20, 2020
Supplemental Funding Ballot Question
June 23, 2020  
Submit to DEP for SRF "Approval to Award"
July 20, 2020
Execute ContractsAugust 14, 2020
Collection System Construction BeginsSeptember 8, 2020
Wastewater Treatment Facility Construction BeginsSeptember 8, 2020
Construction CompletedJuly 2022